Ceremonial laying of the foundation stone

Construction of the new Sonnenschule building is progressing rapidly

In his speech, Mayor Michael Gerdhenrich outlined the progress of the building work to date, which is fully on schedule, and thanked everyone involved, particularly the school community. Headteacher Claudia Sander-Braunert explained what had been placed in the time capsule: a daily newspaper, coins, mementoes of the school and messages to the children of the future. A school choir added to the programme and expressed, through music, the children’s excitement at moving into the new building.

Progress to date and the remaining construction schedule:

  • To ensure that school operations could continue during the construction work, a temporary school playground and a staff car park were set up in April on the former playground next to the Sonnenschule.
  • This was followed by the preliminary earthworks and civil engineering works, and the school playground equipment and tarmac surfaces were dismantled.
  • The groundwork began in early July. The foundations and floor slabs were completed in early September.
  • Structural work is currently underway, involving the assembly of precast concrete elements. The auditorium and canteen wing is now complete. Work on the two-storey administration block (Building B) and the first school wing (Building D) has been underway since the last week of September. Both sections are due to be completed by mid-October.
  • The remaining school wing (BT C) is expected to be completed by the end of October.
  • Roof waterproofing work is taking place alongside the structural work.
  • During the assembly of the precast concrete elements for the two school wings and the administration block, the window openings have already been incorporated into the walls, meaning that the building envelope is essentially complete. Only the external doors and the mullion-and-transom façade will be fitted on site.
  • Installation of the mullion-and-transom façades will begin at the end of October.
  • Work on the timber façade will begin at around the same time.
  • The building envelope is due to be fully enclosed by December.
  • The finishing trades are brought in as and when the individual sections of the building are completed.

A bright future for the Sonnenschule

Plenty of space for learning and state-of-the-art primary school standards: the Sonnenschule school community, together with the school’s governing body, is looking forward to the new building, which is taking shape right next to the old school. At the primary school network’s current main site on Obere Wilhelmstraße, a modern and forward-looking primary school is being built with a total floor area of around 4,500 square metres. The building, currently under construction, meets the requirements of contemporary educational practice and offers bright classrooms, flexible learning spaces and a high-performance digital infrastructure. The outdoor area is also being designed to be close to nature and developed as a versatile space for physical activity and learning.

The space allocation plan is based on the guidelines set out in the local authority’s school development plan for all primary schools. Particular attention is paid to all-day provision, so that pupils have access to a comprehensive and varied learning and care environment.

Another key focus is on sustainable and resource-efficient construction methods. The plans include energy-efficient building services, durable materials and cost-effective operation throughout the building’s entire life cycle.

Goldbeck Nord GmbH is carrying out the project under a turnkey contract. A large proportion of the new building is being constructed using a systematic, industrially prefabricated method. Funding is provided by the city’s budget and by federal and state funding schemes.

Handover of the building is scheduled for August 2027. Full completion, including the outdoor facilities, is due to take place in March 2028.

Graphic
Goldbeck Nord GmbH


Facts and figures:

Execution period: March 2026 to probably March 2028
Funding: The construction project is being funded by the state of North Rhine-Westphalia and the federal government with a total of around 2.3 million euros with funds from the KfW Bank and through the funding guideline for all-day expansion.
Costs: The total costs are estimated at around 24 million euros.
General contractor: Goldbeck Nord GmbH Bielefeld

Sonnenschule primary school alliance:

Around 326 pupils in 14 classes (at the Beckum and Vellern sites) are currently attending the Sonnenschule. At the Beckum site, there are currently around 252 children enrolled, spread across 11 classes.