Redesign of the eastern Hellbach valley
Die Neugestaltung des östlichen Hellbachtals in Neubeckum ist ein Leitprojekt aus dem im Jahr 2020 erarbeiteten Integrierten Städtebaulichen Entwicklungskonzept (ISEK) für Neubeckum. Darin heißt es, das östliche Hellbachtal als Freizeit- und Erholungsort für alle Alters- und Nutzergruppen und unter Berücksichtigung der Aspekte Barrierefreiheit, Klimaschutz und Klimaanpassung umzugestalten. Die Neugestaltung des Tales geht einher mit einer gesetzlich erforderlichen gewässerökologischen Umgestaltung des Hellbachs. Für die Gewässerbaumaßnahmen wird aktuell ein Planfeststellungsverfahren durchgeführt.

The Hellbach, which runs through the eastern Hellbach valley and is partially dammed ("Hellbach pond"), is to be restored to a good ecological status by the city of Beckum (Sections 6 and 27 of the Water Resources Act). The measures required to achieve this goal are described in the implementation roadmaps of the state of North Rhine-Westphalia and must be implemented by 2033 at the latest. For the Hellbach in this section, specific measures are required for the dismantling of transverse structures in the eastern forest area, the removal of the impoundment and ecological improvement through the creation of near-natural watercourse conditions (see profile DE_NRW_3282_7802 at www.flussgebiete.nrw.de).
Zum Einstieg in den Planungsprozess hat die Verwaltung im September 2023 einen Planungsauftrag an die DTP Landschaftsarchitekten GmbH aus Essen vergeben. Für den Gewässerumbau hat das Planungsbüro die Fischer Teamplan Ingenieurbüro GmbH aus Erftstadt (Standort Düsseldorf) hinzugezogen. Die Planungsbüros haben einen freiraumplanerischen Entwurf erarbeitet, der den städtebaulichen und gewässerökologischen Vorgaben entspricht. Der Ausschuss für Stadtentwicklung hat in seiner Sitzung am 13.10.2026 den Entwurf und die weitere Vorgehensweise vorbehaltlich des gewässerrechtlichen Planfeststellungsbeschlusses beschlossen. Mit dem Planfeststellungsbeschluss rechnet die Stadt Beckum bis Ende 2026.
Questions and answers:
Why does the city want and need to tackle this project?
The redesign of the eastern Hellbachtal in Neubeckum is a flagship project from the integrated urban development concept (ISEK) for Neubeckum, which was developed in 2020. It states that the eastern Hellbachtal should be redesigned as a leisure and recreation centre for all age and user groups, taking into account aspects such as accessibility, climate protection and climate adaptation. On the basis of the ISEK, urban development funding can be acquired for this measure for a limited period of time - probably for the last time in 2026.
The wishes formulated in the ISEK Neubeckum for the renewal of the path over the dam and the desilting of the Hellbach pond are contrary to the objectives of water protection following a comprehensive basic investigation and analysis. In accordance with sections 6 and 27 of the Water Resources Act (WHG), the city of Beckum must restore the Hellbach, which is partially dammed, to a good ecological condition. The measures required to achieve this goal are described in the implementation roadmaps of the state of North Rhine-Westphalia and must be implemented by 2033.
The administration's interpretation is clearly confirmed in a letter from the district of Warendorf dated 13 February . It states: "The damming of the Hellbach and the so-called Hellbach pond, which is thus perceptible, represents a massive migration barrier for upstream and downstream migration of aquatic life in the Hellbach watercourse. The damming of the Hellbach also prevents sediment transport. This disrupts the naturally interconnected habitat of a watercourse.
Gibt es eine Alternative, zum Beispiel die Entschlammung des Teiches und eine Fischtreppe?
In the course of the planning process, after extensive basic research and subsequent examination of the options, it was determined that complete preservation of the Hellbach pond in its current form is not possible for water law reasons.
At best, the Hellbach pond can be retained in a smaller form, as space is required to separate the course of the Hellbach from the pond. However, this option cannot be realised for reasons of funding, management or design.
The example mentioned here of installing a fish ladder and desilting and maintaining the existing impounded water surface cannot be realised either, as it does not meet the legal requirements. The impounded area as such would continue to represent an obstacle to river continuity, as aquatic organisms would not be able to pass through it.
This was clearly confirmed by the Warendorf district in its statement.
Does the measure have an impact on flood protection?
Flood protection concerns are taken into account as part of the approval of this watercourse renaturalisation. A prohibition of deterioration applies. Accordingly, it must be ensured that the existing flood situation in this area does not change significantly. In principle, watercourse renaturalisation and floodplain development contribute to flood protection.
Does the measure threaten to dry out the Hellbach and cause a loss of biodiversity?
The dammed Hellbach is an artificially created habitat. The perceived "pond" is not a still body of water, but a dammed watercourse, in this case the Hellbach. This artificially created body of water is being replaced by the restoration of a natural watercourse in order to ensure ecological continuity for the aquatic life of the Hellbach and improve its ecological status. In the upper reaches of a watercourse, low water levels and even dry sections can occur naturally, but these do not lead to a loss of biodiversity in this habitat.
The perceived "pond" currently means that creatures from the stream can no longer orientate themselves in the dammed water surface and cannot move on due to the lack of current.
The current species population, adapted to this artificial habitat, will not remain the same in the future. However, the renaturalisation of the watercourse will create new habitats that will primarily promote the natural occurrence of species and increase biodiversity. Species protection issues will be examined as part of the planning process; in principle, the planned measure will lead to an ecological enhancement of the entire area.
Is the measure not too expensive in the current financial situation?
Nach aktueller Kostenberechnung belaufen sich die Gesamtkosten (einschließlich der politisch beschlossenen barrierefreien Querung zwischen der Adolf-Kolping-Straße und der Straße Am Hellbach) unter Berücksichtigung etwaiger allgemeiner Baupreissteigerungen auf rund 2,3 Millionen Euro für den Gewässerbau und rund 2,7 Millionen Euro für die städtebauliche Aufwertung.
Es wird aktuell davon ausgegangen, dass die Maßnahme zum Gewässerbau letztendlich mit 80 Prozent aus Fördermitteln (etwa 1,8 Millionen Euro) nach der Förderrichtlinie Hochwasserrisikomanagement und Wasserrahmenrichtlinie förderfähig ist. Für die städtebauliche Aufwertung kann mit Städtebaufördermitteln in Höhe von 1,6 Millionen Euro (60 Prozent Förderquote) gerechnet werden. Der Eigenanteil der Stadt Beckum für das Gesamtprojekt liegt somit bei etwa 1,5 Millionen Euro.
Wie mit der Stellungnahme des Kreises Warendorf eindeutig bestätigt wurde, ist eine Aufgabe des „Teiches” bis 2033 zwingend erforderlich. Ob das Förderprogramm Hochwasserrisikomanagement und Wasserrahmenrichtlinie jedoch bis 2033 erhalten bleibt, ist unklar. Die Möglichkeit der Akquise von Städtebaufördermitteln für die städtebauliche Aufwertung zu einem späteren Zeitpunkt ist ebenso unklar. Aktuell können für die Maßnahme bis 2026 Städtebaufördermittel beantragt werden. Für beide Förderprogramme wurden die entsprechenden Anträge gestellt.
If the measure is implemented at a later date, the financial burden on the budget may therefore be significantly higher.
Video message from the mayor on the topic (forwarding to the Facebook page of the city of Beckum)