Klarastraße completed

Adverse weather conditions and challenging ground conditions have led to a delay of around one month. In consultation with the utility companies, additional empty conduits have been laid for a future fibre-optic network to facilitate subsequent development.

As part of the project, the entire road structure was renewed. In addition, a single-sided, regulation-compliant pavement with tactile elements was constructed. On the opposite side of the road, the carriageway was edged with a kerb. Alternating parking bay markings improve road safety and help to reduce noise pollution by encouraging drivers to slow down.

The construction project was completed within the estimated budget of 290,000 euros.